Ghodegaon 12 MW – Progress Dashboard

Overall Progress
25.72%
Total Completed
3,170.1

units completed

Total Planned
12,326

total units

Active Activities
9

of 9 started

Activity Progress (Latest Report)
Progress Timeline
Activity Details

Fencing Installation

Chain Link Fencing

50%
Total: 1320 metersDone: 660 meters

Module Installation

MMS Work (Module Mounting Structure)

28%
Total: 930 unitsDone: 260 units

Structure Erection

MMS Work (Module Mounting Structure)

22%
Total: 12 MWDone: 2.6 MW

Control Room Construction

MCR Work (Main Control Room)

100%
Total: 1 buildingDone: 1 building

Inverter Room Setup

ICR Work (Inverter Control Room)

50%
Total: 1 roomDone: 0.5 room

6 sq mm DC Cabling

DC Cable Work

19%
Total: 5000 metersDone: 950 meters

300 sq mm DC Cabling

DC Cable Work

26%
Total: 2000 metersDone: 520 meters

AC Cable Laying

AC Cable Work

25%
Total: 3000 metersDone: 750 meters

String Main Box Installation

SMB Installation

42%
Total: 62 boxesDone: 26 boxes