Overall Progress
25.72%
Total Completed
3,170.1
units completed
Total Planned
12,326
total units
Active Activities
9
of 9 started
Activity Progress (Latest Report)
Progress Timeline
Activity Details
Fencing Installation
Chain Link Fencing
Total: 1320 metersDone: 660 meters
Module Installation
MMS Work (Module Mounting Structure)
Total: 930 unitsDone: 260 units
Structure Erection
MMS Work (Module Mounting Structure)
Total: 12 MWDone: 2.6 MW
Control Room Construction
MCR Work (Main Control Room)
Total: 1 buildingDone: 1 building
Inverter Room Setup
ICR Work (Inverter Control Room)
Total: 1 roomDone: 0.5 room
6 sq mm DC Cabling
DC Cable Work
Total: 5000 metersDone: 950 meters
300 sq mm DC Cabling
DC Cable Work
Total: 2000 metersDone: 520 meters
AC Cable Laying
AC Cable Work
Total: 3000 metersDone: 750 meters
String Main Box Installation
SMB Installation
Total: 62 boxesDone: 26 boxes
| Activity | Category | Total Qty | Completed | Progress % |
|---|---|---|---|---|
| Fencing Installation | Chain Link Fencing | 1320 meters | 660 meters | 50% |
| Module Installation | MMS Work (Module Mounting Structure) | 930 units | 260 units | 28% |
| Structure Erection | MMS Work (Module Mounting Structure) | 12 MW | 2.6 MW | 22% |
| Control Room Construction | MCR Work (Main Control Room) | 1 building | 1 building | 100% |
| Inverter Room Setup | ICR Work (Inverter Control Room) | 1 room | 0.5 room | 50% |
| 6 sq mm DC Cabling | DC Cable Work | 5000 meters | 950 meters | 19% |
| 300 sq mm DC Cabling | DC Cable Work | 2000 meters | 520 meters | 26% |
| AC Cable Laying | AC Cable Work | 3000 meters | 750 meters | 25% |
| String Main Box Installation | SMB Installation | 62 boxes | 26 boxes | 42% |