Report – 23 March 2024
Report Date
23 March 2024
Created By
Project Manager
Fencing Installation
Chain Link Fencing
Total
1320 meters
Daily
180 meters
Cumulative
660 meters
Module Installation
MMS Work (Module Mounting Structure)
Total
930 units
Daily
80 units
Cumulative
260 units
Structure Erection
MMS Work (Module Mounting Structure)
Total
12 MW
Daily
0.8 MW
Cumulative
2.6 MW
Control Room Construction
MCR Work (Main Control Room)
Total
1 building
Daily
0.4 building
Cumulative
1 building
Inverter Room Setup
ICR Work (Inverter Control Room)
Total
1 room
Daily
0.3 room
Cumulative
0.5 room
6 sq mm DC Cabling
DC Cable Work
Total
5000 meters
Daily
280 meters
Cumulative
950 meters
300 sq mm DC Cabling
DC Cable Work
Total
2000 meters
Daily
160 meters
Cumulative
520 meters
AC Cable Laying
AC Cable Work
Total
3000 meters
Daily
220 meters
Cumulative
750 meters
String Main Box Installation
SMB Installation
Total
62 boxes
Daily
8 boxes
Cumulative
26 boxes
| Activity | Category | Total Qty | Daily Completed | Total Completed | Progress % |
|---|---|---|---|---|---|
| Fencing Installation | Chain Link Fencing | 1320 meters | 180 meters | 660 meters | 50.00% |
| Module Installation | MMS Work (Module Mounting Structure) | 930 units | 80 units | 260 units | 27.96% |
| Structure Erection | MMS Work (Module Mounting Structure) | 12 MW | 0.8 MW | 2.6 MW | 21.67% |
| Control Room Construction | MCR Work (Main Control Room) | 1 building | 0.4 building | 1 building | 100.00% |
| Inverter Room Setup | ICR Work (Inverter Control Room) | 1 room | 0.3 room | 0.5 room | 50.00% |
| 6 sq mm DC Cabling | DC Cable Work | 5000 meters | 280 meters | 950 meters | 19.00% |
| 300 sq mm DC Cabling | DC Cable Work | 2000 meters | 160 meters | 520 meters | 26.00% |
| AC Cable Laying | AC Cable Work | 3000 meters | 220 meters | 750 meters | 25.00% |
| String Main Box Installation | SMB Installation | 62 boxes | 8 boxes | 26 boxes | 41.94% |