Report – 23 March 2024

Report Information

Report Date

23 March 2024

Created By

Project Manager

Activity Progress Details

Fencing Installation

Chain Link Fencing

50.0%

Total

1320 meters

Daily

180 meters

Cumulative

660 meters

Module Installation

MMS Work (Module Mounting Structure)

28.0%

Total

930 units

Daily

80 units

Cumulative

260 units

Structure Erection

MMS Work (Module Mounting Structure)

21.7%

Total

12 MW

Daily

0.8 MW

Cumulative

2.6 MW

Control Room Construction

MCR Work (Main Control Room)

100.0%

Total

1 building

Daily

0.4 building

Cumulative

1 building

Inverter Room Setup

ICR Work (Inverter Control Room)

50.0%

Total

1 room

Daily

0.3 room

Cumulative

0.5 room

6 sq mm DC Cabling

DC Cable Work

19.0%

Total

5000 meters

Daily

280 meters

Cumulative

950 meters

300 sq mm DC Cabling

DC Cable Work

26.0%

Total

2000 meters

Daily

160 meters

Cumulative

520 meters

AC Cable Laying

AC Cable Work

25.0%

Total

3000 meters

Daily

220 meters

Cumulative

750 meters

String Main Box Installation

SMB Installation

41.9%

Total

62 boxes

Daily

8 boxes

Cumulative

26 boxes