Report – 22 March 2024

Report Information

Report Date

22 March 2024

Created By

Project Manager

Activity Progress Details

Fencing Installation

Chain Link Fencing

36.4%

Total

1320 meters

Daily

170 meters

Cumulative

480 meters

Module Installation

MMS Work (Module Mounting Structure)

19.4%

Total

930 units

Daily

70 units

Cumulative

180 units

Structure Erection

MMS Work (Module Mounting Structure)

15.0%

Total

12 MW

Daily

0.7 MW

Cumulative

1.8 MW

Control Room Construction

MCR Work (Main Control Room)

60.0%

Total

1 building

Daily

0.3 building

Cumulative

0.6 building

Inverter Room Setup

ICR Work (Inverter Control Room)

20.0%

Total

1 room

Daily

0.2 room

Cumulative

0.2 room

6 sq mm DC Cabling

DC Cable Work

13.4%

Total

5000 meters

Daily

250 meters

Cumulative

670 meters

300 sq mm DC Cabling

DC Cable Work

18.0%

Total

2000 meters

Daily

140 meters

Cumulative

360 meters

AC Cable Laying

AC Cable Work

17.7%

Total

3000 meters

Daily

200 meters

Cumulative

530 meters

String Main Box Installation

SMB Installation

29.0%

Total

62 boxes

Daily

7 boxes

Cumulative

18 boxes