Report – 21 March 2024

Report Information

Report Date

21 March 2024

Created By

Project Manager

Activity Progress Details

Fencing Installation

Chain Link Fencing

23.5%

Total

1320 meters

Daily

160 meters

Cumulative

310 meters

Module Installation

MMS Work (Module Mounting Structure)

11.8%

Total

930 units

Daily

60 units

Cumulative

110 units

Structure Erection

MMS Work (Module Mounting Structure)

9.2%

Total

12 MW

Daily

0.6 MW

Cumulative

1.1 MW

Control Room Construction

MCR Work (Main Control Room)

30.0%

Total

1 building

Daily

0.2 building

Cumulative

0.3 building

Inverter Room Setup

ICR Work (Inverter Control Room)

0.0%

Total

1 room

Daily

0 room

Cumulative

0 room

6 sq mm DC Cabling

DC Cable Work

8.4%

Total

5000 meters

Daily

220 meters

Cumulative

420 meters

300 sq mm DC Cabling

DC Cable Work

11.0%

Total

2000 meters

Daily

120 meters

Cumulative

220 meters

AC Cable Laying

AC Cable Work

11.0%

Total

3000 meters

Daily

180 meters

Cumulative

330 meters

String Main Box Installation

SMB Installation

17.7%

Total

62 boxes

Daily

6 boxes

Cumulative

11 boxes