Report – 20 March 2024
Report Date
20 March 2024
Created By
Project Manager
Fencing Installation
Chain Link Fencing
Total
1320 meters
Daily
150 meters
Cumulative
150 meters
Module Installation
MMS Work (Module Mounting Structure)
Total
930 units
Daily
50 units
Cumulative
50 units
Structure Erection
MMS Work (Module Mounting Structure)
Total
12 MW
Daily
0.5 MW
Cumulative
0.5 MW
Control Room Construction
MCR Work (Main Control Room)
Total
1 building
Daily
0.1 building
Cumulative
0.1 building
Inverter Room Setup
ICR Work (Inverter Control Room)
Total
1 room
Daily
0 room
Cumulative
0 room
6 sq mm DC Cabling
DC Cable Work
Total
5000 meters
Daily
200 meters
Cumulative
200 meters
300 sq mm DC Cabling
DC Cable Work
Total
2000 meters
Daily
100 meters
Cumulative
100 meters
AC Cable Laying
AC Cable Work
Total
3000 meters
Daily
150 meters
Cumulative
150 meters
String Main Box Installation
SMB Installation
Total
62 boxes
Daily
5 boxes
Cumulative
5 boxes
| Activity | Category | Total Qty | Daily Completed | Total Completed | Progress % |
|---|---|---|---|---|---|
| Fencing Installation | Chain Link Fencing | 1320 meters | 150 meters | 150 meters | 11.36% |
| Module Installation | MMS Work (Module Mounting Structure) | 930 units | 50 units | 50 units | 5.38% |
| Structure Erection | MMS Work (Module Mounting Structure) | 12 MW | 0.5 MW | 0.5 MW | 4.17% |
| Control Room Construction | MCR Work (Main Control Room) | 1 building | 0.1 building | 0.1 building | 10.00% |
| Inverter Room Setup | ICR Work (Inverter Control Room) | 1 room | 0 room | 0 room | 0.00% |
| 6 sq mm DC Cabling | DC Cable Work | 5000 meters | 200 meters | 200 meters | 4.00% |
| 300 sq mm DC Cabling | DC Cable Work | 2000 meters | 100 meters | 100 meters | 5.00% |
| AC Cable Laying | AC Cable Work | 3000 meters | 150 meters | 150 meters | 5.00% |
| String Main Box Installation | SMB Installation | 62 boxes | 5 boxes | 5 boxes | 8.06% |